Tip: Use ctrl and + keys to zoom in for a clearer view of screenshots.
Importing Data from Microsoft Project
Start by hitting Cmd/Ctrl+K to open the action menu.
From here you'll be prompted to upload your .mpp file.
Once you've selected your file for upload, Integrate will analyze the file and offer you two options:
Final step, review your data and then hit 
Here's brief demonstration of this method:
Importing Data from .csv
Data Preparation
In your Excel/Numbers/Google Sheets, start by dissecting project information into separate sheets (e.g: sheet 1 = Project 1, sheet 2 = Project 2).
Make sure there are at least four columns labelled with:
Name
Start Date: format MM/DD/YYYY
Target Date: format MM/DD/YYYY
Driver Type: for each line label as a 'requirement', 'task', 'component', or 'milestone'.
Nested Driver Type: use as a separate line under the Driver type line describe a sub driver.
Optional columns:
Status: for each line label as 'To Do', 'In Progress', 'Complete'.
Description: add any additional information attached to the item.
Resource Cost: add the number of hours each driver will require for completion (Workload).
Collaborator email: assign collaborators from your organization automatically by listing them using this format: [email protected], [email protected], [email protected].
Collaborator role: assign roles based on collaborators. Roles will line up with the order collaborator emails are listed. Ex: Editor ([email protected]), Editor, Viewer.
Assignee: label an assignee from the list of collaborators.
Tip: At the end of this article there is a reference template available for download.
Data Ingestion
In Integrate, start by creating the Project (this project should match the Sheet you just prepared).
From the card, go to
and select:
Here's a brief demonstration of this method:
Exporting Data
Go to the card and navigate to 
This will export your data as a .csv file.