Baselines

Display changes from baseline.

Baselines let you see how your schedule has changed over time. When you set a baseline date, Integrate displays the item's position it held on that date, enabling you to compare where work was planned against where it stands now.

Start by going to the display menu.

Green values show items that have moved left on the gantt.

Red values show items that have moved to the right on the gantt.

Tip: Turn on 'Show Date Ranges' to display live date changes on the Gantt.

Note: Baseline date selection needs to be from a point where the project existed. If you select a date that pre-dates the project, nothing will display.